Lappeenranta: Power outage on campus 24.6.-25.6.
17.06.2025 (publishing time)
SYK will be carrying out transformer maintenance from 24.6. - 25.6.2025
This will cause a power outage in buildings 1-7 starting from 24.6 at 16:00 and ending on 25.6 at 04:00.
The power in buildings 1-7 will be off during that time, access control will also stop working!
- The power outage on the entire campus will start at 16:00
- The power on the entire campus will be restored to normal by 04:00 or earlier depending on the progress of the maintenance work'
Summary – Tuesday 24.6.2025
- The entire campus's building services shutdowns (e.g. ventilation) will begin at 14:00
- The entire campus's power outage will begin at 16:00
- The maintenance of substations M1 and M7 will be completed by 22:00 and their electricity will be restored
- The electricity of substation M4 Hemsö will be restored by 22:00 (M7 feeds M4)
- The maintenance of substations M2, M3 and M5 will continue directly after M1 and M7
- The electricity of substations M2, M3 and M5 will be restored by 04:00
The electricity of the entire campus will be restored to normal by 04:00 or earlier depending on the progress of the maintenance work